Deliver to 
Free Shipping
  • Served Customers
  • Secure Payments
  • Served Customers
24/7 Live Chat
Construction Project Administration 10th Edition By Fisk  Test Bank  Updated 2025 0
Construction Project Administration 10th Edition By Fisk  Test Bank  Updated 2025 0

Construction Project Administration 10th Edition By Fisk - Test Bank - Updated 2025

ExamExperts
40 sales
NaN
$12.00 
 & Instant Download
Payment Methods:
About this item

CHAPTER 1

ANSWERS

1.         Project time, cost, and quality 

2.         Professional Construction Manager (under direct contract with the Owner as the Owner’s representative)

3.         Either the planning or the conceptual phase

4.         Any of the listed alternatives

5.         True (This usually means between the Resident Project Representative and the Contractor’s Superintendent or Project Manager at the site)

6.         Working relationships among the parties through a mutually-developed, formal strategy of commitment and communication.

7.         (1). Creation of partnering charter; (2). Develop issue-resolution process; (3). Develop joint evaluation process; (4). Discuss individual roles and concerns; and (5). present a facilitated workshop

8.         It should be addressed in the specifications

9.         True; (CQC is an acronym for Contractor Quality Control)

10.       (1) Advertising; (2) Bid Opening; (3) Award of Contract; (4) Sign Agreement; (5) Notice to Proceed.

11.       The Owner and the Contractor each designate a single person who is the sole authorized spokesperson to make commitments or issue orders to the Contractor. Ideally, this should be the Resident Project Representative for the Owner and the Project Superintendent or Project Manager for the Contractor. ALL orders to the Contractor MUST be issued through this one person.

12.       On public contracts, designer and the contractor selection methods conflict. On public contracts the designer is selected on the basis of a negotiated contract offered to the most qualified party; in contrast, on public contracts the contractor must be selected on the basis of sealed bids, with award made to the lowest responsive, responsible bidder based upon price only.


CHAPTER 2

ANSWERS

1.         The level of authority implied by the position held by the person issuing a directions or orders;

            e.g., Project Manager, Chief Engineer, Architect, Resident Project Representative, City Engineer,

            Director of Public Works, etc.

2.         The authority given the Resident Project Representative by the Project Manager, or the authority allowed a construction manager by the Owner

3.         Two dangers; (1) exposure to tort liability, and (2) acceptance of responsibility by the Owner for the success or failure of the affected construction.

4.         Promptly after delivery to the project site or other location under the Owner’s control

5.         No. (Recommend use of federal guidelines. Under the Code of Federal Regulations, a Contracting Officer is permitted to delegate almost all contract administration functions to the field with but two exceptions. By law he or she may not delegate authority to act on matters affecting either contract time or cost. (48 CFR 43.102). On non-federal work, the Contracting Officer position can be equated to that of the Project manager.

6.         No. All orders and instructions MUST be issued through the General or Prime Contractor's representative.

7.         The Owner. While the Engineer may be given the authority to stop the work at the specific direction of the owner on a case-by-case basis, that right should not be given to the Engineer to stop the work on his or her own authority. This is to avoid the dangers of exposure to tort liability by the Engineer. (c.f.  EJCDC 1910-8 (1996) General Conditions of the Construction Contract, Article 13.05 entitled “OWNER May Stop the Work”)

8.         None of the practices listed are acceptable.

9.         False. To do so is tantamount to directing the means and methods of performing the work.

10.       False: (The inspector should notify the general contractor and instruct him or her to notify the subcontractor that correction must be made.)

11.       Contractual; delegated; and legal

12.           Reject the method as being incapable of meeting the project specifications and require the contractor to submit a proposed alternative method that will meet the specifications.  If the contractor challenges the decision to reject, a demonstration of the rejected method may be considered for evaluation.


free shipping

Free Shipping

24/7 chat

24/7 Live Chat

30 day returns

Secure Payments

Questions 

No reviews

This product has no reviews yet